Substructure & Piers
delayed
Pier Column Casting
Sub-Contractor:
Apex Structural Sub-Contractors
(SCWO/APEX/088)
Date Assigned:
2026-07-20
Target Completion:
2026-08-30
Total Scope:
600 CuM
Executed:
120 CuM
Balance Work Qty:
480 CuM
₹ 37,44,000
Reason for Delay
RMC batching plant conveyor breakdown caused
4-day pour halt.