Master Schedules, Work Orders, RA Billing & Material Verification
| Sub-Contractor | WO / BOQ | Structure & Item | Date of Assignment | Date of Completion | Scope / Executed Qty | Status | Progress Remarks & Delay Reasons | Action |
|---|---|---|---|---|---|---|---|---|
|
Apex Structural
Sub-Contractors
|
SCWO/APEX/088
PRJ-001 |
Substructure & Piers
Pile Cap Concrete
Unit: CuM
|
15 Jul 2026 | 15 Aug 2026 |
420 / 850
49.4%
|
Started |
Formwork for Pier Caps P42-P48.
|
|
|
Apex Structural
Sub-Contractors
|
SCWO/APEX/088
PRJ-001 |
Substructure & Piers
Pier Pedestal Fabrication
Unit: MT
|
18 Jul 2026 | 20 Aug 2026 |
30 / 95
31.6%
|
Started |
Template alignment in progress.
|
|
|
Star Bar-Bending
Works
|
SCWO/STAR/042
PRJ-001 |
Substructure & Piers
Pier Pedestal Fabrication
Unit: MT
|
01 Aug 2026 | 25 Aug 2026 |
0 / 95
0%
|
Not Started |
Pier pedestal templates queue.
|
|
|
Vanguard Piling
Rigs
|
SCWO/VANG/015
PRJ-002 |
Adyar Block B Structure Core
Anchorage Installation
Unit: Nos.
|
18 Jul 2026 | 10 Aug 2026 |
45 / 150
30%
|
Delayed |
Anchorage block sets installation.
Reason for Delay
Port customs clearance hold for imported
anchorage castings.
|
|
|
Vanguard Piling
Rigs
|
SCWO/VANG/015
PRJ-002 |
Adyar Block B Structure Core
Concrete Core Walls
Unit: CuM
|
05 Aug 2026 | 15 Sep 2026 |
0 / 1,200
0%
|
Not Started |
Lift core wall casting staging.
|