Planning & Quantity Surveying (QS) Engine

Master Schedules, Work Orders, RA Billing & Material Verification

WBS-1.1 Site Preparation & Land Demarcation CPM Critical Path
Completed
Start: 2026-01-10 → End: 2026-02-15
WBS Weightage: 5%
Progress: 100%
WBS-1.2 Deep Foundation Piling & Soil Testing CPM Critical Path
Completed
Start: 2026-02-16 → End: 2026-05-30
WBS Weightage: 20%
Progress: 100%
WBS-2.1 Pier Structure & Pier Cap Concreting CPM Critical Path
In Progress
Start: 2026-06-01 → End: 2026-10-15
WBS Weightage: 30%
Progress: 78%
WBS-2.2 Prestressed Girder Erection & Deck Launching CPM Critical Path
In Progress
Start: 2026-10-16 → End: 2027-02-28
WBS Weightage: 25%
Progress: 15%
WBS-3.1 Track Bed Layout & MEP Electrical Grid Normal
Planning
Start: 2027-03-01 → End: 2027-06-30
WBS Weightage: 20%
Progress: 0%